The Solution:
Our Solution Alspec engaged Resinject to propose a suitable solution to re-level and stabilise the affected concrete slabs, that would have the production line continuing at its normal rate of operation, down time was not an option. Subsequently, Resinject’s experienced consultants promptly attended the site and assessed the foundation issues.
After looking at the building plans it was discovered that the slabs had been built on 4 metres of poorly compacted fill materials. Over a period of time, the fill has experienced a degree of settlement which has transferred to the concrete slabs. Some areas of the slab were seeing a drop of up to 120mm. This was deemed as the primary mechanism causing the settling and subsiding of the foundations.
To raise and re-level the foundation slabs, Resinject proposed a treatment plan consisting of a grid of injection points across the entire slab area of 10,000 square metres. This treatment would prevent their production line from getting knocked out due to movement of their lasers.
Following this, a series of stabilising piers were proposed to a depth of 4m centres around the perimeter of the slab to counteract any future subsidence by improving the load-bearing capacityof the ground ensuring longevity of the re-leveling works. Alspec agreed to the proposed solution and Resinject’s services were booked in for shortly thereafter.
To raise and re-level the foundation slabs, Resinject proposed a treatment plan consisting of a grid of injection points across the entire slab area of 10,000 square metres. This treatment would prevent their production line from getting knocked out due to movement of their lasers. Following this, a series of stabilising piers were proposed to a depth of 4m centres around the perimeter of the slab to counteract any future subsidence by improving the load-baring capacity of the ground ensuring longevity of the re-leveling works. Alspec agreed to the proposed solution and Resinject’s services were booked in for shortly thereafter.
After completing the proposed injection solution, Resinject re-measured the levels of the foundation slabs and confirmed that the slab had been stabilised and re-levelled.
Furthermore, Resinject services were completed within a very tight timeframe with two crews operating on a 24-hour basis for a week thereby ensuring that Alspec experienced zero downtime. With the foundations successfully raised, relevelled, and stabilised, the production line has been protected from unnecessary and costly interruptions caused by foundational movement.